top of page
  • jphelan98

Case Study

Updated: Dec 15, 2020

The Challenge:

  1. To provide our customer, a major construction equipment dealer, with a building supported overhead crane system for a new facility in Kentucky. The job incorporated two 10 ton single girder overhead cranes.

Special Consideration:

  1. The general contractor needed design build capabilities for the overhead crane and runway systems. Single girder overhead cranes with low headroom hoists were utilized to minimize overhead crane and building steel costs.

Results:

  1. The general contractor maximized the strength of the building while Crane-Tec supplied a complete overhead crane system and the owner maximized floor space. The overhead cranes were weight tested and turned over to the customer ahead of schedule.

For Immediate Results Call 800-755-6378 CRANE-TEC.COM

12 views0 comments
bottom of page