Author Archive for: Julie Phelan

 

How do you make a frog

How do you make a Frog

The Challenge:

To provide a building supported crane system with two 25 Ton capacity and one 10 Ton capacity long span heavy duty cranes.  The crane system was to be designed into the metal building structure of a regional railroad manufacturer for their “Frog” manufacturing.  Frogs are railroad exchanges that divert trains from one line to another.

Special Considerations:

Owner application required heavy duty high speed cranes.  Independent tie back runway systems were designed to maximize the strength of the pre-engineered metal building.

Our Team Approach:

Working with the owner and the General Contractor we were able to design a building that supported the loads of 3 heavy duty high speed bridge cranes.  We installed two 25 ton cranes, each with a 5 ton auxilliary hoist, and a 10 ton crane.  These allowed the manufacturer to have three work areas which stream-lined their manufacturing.

Results:

Crane Tec supplied a turn-key crane system on time and within budget

                                

 

John Deere Dealer Crane

 

 

 

The Challenge:

To provide our customer, a John Deere Dealer, with an integrated crane system for a new facility in Indiana.
The project incorporated two 5-ton underhung cranes and runway systems.

Special Considerations:

The general contractor needed design loading for the building and runway system. Single girder cranes with low headroom hoists were used to minimize runway and building steel costs.

Crane-Tec engineers using the metal building drawing, designed a cost efficient and space saving runway system using the building frames to suspend the runway system. This maximized the strength of the building.
Both cranes were supplied with radio remote controls for safe and precise operation.

Results:

Crane-Tec supplied a complete engineered crane and runway system. The crane system was installed, weight tested, and turned over to the owner on time with a two year warranty.

 

Wooden Building – Crane Installation

The Challenge

To provide our customer, a custom wooden structure and joinery fabricator, with a system that would improve production times and allow them to move large pieces of material safety and more efficiently.

Special Consideration

The company’s production is located in a very unique and
stunning facility made completely out of wood. They needed the ability to load large pieces into milling machines and move finished products
throughout the building.  Crane-Tec was challenged with designing a structural system that worked within their wooden building framework.

Our Team Approach

Crane-Tec worked closely with the customer to learn
their specific needs and expectations of the new system.
With our combined efforts, and after reviewing several options,
solutions included:

  1. Two 2.5 Ton top running single girder cranes.

  2. Radio control operation for each crane, with the option to operate each crane individually, or in tandem. This feature allows the operator to link both cranes together and operate them simultaneously with one single button push, ideal for handling of long pieces of materials.

  3. Special anchors to attach the crane’s steel runway beam to the wooden building haunches.

Results

Crane-Tec delivered a system that exceeds the customer’s expectation and allows them to easily and safely move products throughout their amazing facility.


 

Dual 25 Ton Cranes Case Study

The Challenge

 To provide a crane system to help our customer in their manufacturing of large concrete building panels.

Special Consideration

Our customer needed to move large concrete panels through their high capacity manufacturing process.

Our Team Approach

We worked closely with the customer to learn their manufacturing process, their material handling frequency and their performance expectations.  This resulted in the following:

  • Engineering, design, and installation of

    – Crane runway beams and crane rail on their existing concrete column haunches

    – Two (2) 25 ton top running double box girder cranes

    – Engineered lifting beams to facilitate movement of the large precast panels

  • Cranes were sized for heavy duty usage with high speed hoists, trolleys and bridges.

  • Cranes were equipped with radio remote controls for safe and efficient material handling. The remotes allowed the customer to operate the cranes individually and in tandem.

Results

Crane-Tec provided our customer with a complete turnkey crane system that was customized to their manufacturing needs.

 

Warehouse Expansion Case Study

 

 

 

The Challenge:

To provide our customer, an electric motor manufacturer, with an array of lifting solutions for a large expansion of their facility.

 

Special Consideration

Our customer needed to be able to move large scale electric motors throughout their facility interacting with multiple workstations.

 

Our TEAM Approach:

We worked closely with the customer to learn their specific needs, workflow and expectations, which resulted in the following:           

  • Installing Two 25 Ton top running double girder cranes with a radio control system that allows the cranes to be operated in unison, or individually, with only one hand held remote.
  • Installing eight 1-Ton column mounted jib cranes with electric two-speed chain hoists.
  • Installing a 2-Ton floor mounted jib crane with an electric two-speed chain hoist.

Result:

We provided our customer with a state of the art lifting system solution that maximized their workflow and productivity and was installed on-time and within budget.

 

Vacuum Lifter Case Study

 

The Challenge:

To provide our customer, an industrial metal parts stamping facility, with a safer and more efficient way to load their laser cutting machine.

Special Considerations:

Our customer needed to be able to load the machine with a large piece of sheet metal quickly and safely.  The machine was in a current manufacturing facility which had low ceiling clearance.

 Our TEAM Approach:

Crane-Tec worked closely with the customer to learn their specific needs and expectations of the new system.  With our combined efforts, many options were presented, including:

  • Using the existing building trusses to support a Spanco underhung push-pull bridge, trolley and runway system

  • Installing an R&M electric two speed chain hoist

  • Using an Anver vacuum air lifter with built-in air compressor to lift the sheets with ease.

Result: 

Crane-Tec’s highly skilled installers installed a state of the art lifting system in just under 24 hours, keeping our customer’s production staff with minimal down time. They are now able to load the machine more safely and efficiently.

 

Injection Molding Facility Case Study

The Challenge:

To provide
our customer, an injection molding facility, with a larger capacity crane to fit an existing runway system. The customer was upgrading their facility with larger machines and wanted to add  a 7.5-ton top running crane to their existing 5-ton system.

Special Considerations:

The existing crane, being lower capacity, had a shorter stature on the runway rail. With the customer needing a specific lifting height capability, and the building having a low roof, our engineers and staff were up to the challenge.


Our TEAM Approach:

Crane-Tec worked closely with the customer to learn their specific needs and expectations of the new system. With our combined efforts, many options were presented, including:

  • A double girder crane, which allows the use of smaller beams to achieve the low headroom hook height.

  • Radio control operation which allows the operator to stand at a safe distance from the load and move through the factory freely. 

  • A goose neck connection from beam to end truck to maximize lifting height.

  • Duel hoist to aid in larger lifts and rotating molds for service.

  • A warning light and buzzer to alert others in the building the crane is in motion.

Result:

Crane-Tec delivered a custom built, state of the art crane.  Following up with our customer, our staff was told with this new system, mold change down time has been cut by 2/3.